GBAF Logo
Global Banking & Finance Awards® 2026 Nominations open, free to enter Nominate now →
BHP flags cost overrun at Jansen potash project, to book $2.3 billion charge - Finance news and analysis from Global Banking & Finance Review
Finance

BHP flags cost overrun at Jansen potash project, to book $2.3 billion charge

Published by Global Banking & Finance Review

Posted on June 18, 2026

3 min read

· Last updated: June 18, 2026

Add as preferred source on Google

BHP flags cost overrun at Jansen potash project, to book $2.3 billion charge

Cost Overruns and Delays at Jansen Potash Project

By Sneha Kumar

June 18 (Reuters) - BHP Group on Thursday warned of cost overruns at its Jansen Stage 2 potash project in Canada and said it will book a $2.3 billion charge as higher costs and additional labour hours drive up spending and delay first production.

Background and Project Timeline

This is the third time BHP has blown past its cost and time estimates for the two stages of the project, dealing a major setback to the miner's decade-long plans to diversify from copper and iron ore.

BHP accelerated the development of Jansen in 2022 on bets that the Russia-Ukraine conflict would disrupt fertiliser supply and boost prices. But inflation, design changes and lower productivity drove up costs and delayed first output.

Factors Contributing to Overruns

"It is noted that cost and schedule pressures are driven by inflationary and real cost escalation, design development and scope changes, lower productivity outcomes and additional labour hours and material quantities to complete," BHP said in its statement.

Financial Impact and Analyst Reactions

Updated Investment Estimates

Its total investment estimate for the project's second stage is now expected to be $6.9 billion, up from $4.9 billion approved in 2023. First production is now expected in late financial year 2031.

Analyst Commentary

Jefferies analysts said the cost increase exceeded expectations and called the update "unhelpful" due to a poor foreseeable outlook for potash.

"We reiterate our hold rating on BHP as we see better value elsewhere in mining for now."

Stage 1 and Stage 2 Progress

Stage 1 Cost and Timeline

The first stage of the project is expected to cost $8.4 billion, nearly 50% higher than what was approved in 2021, and remains on track to begin production in mid-2027.

Stage 2 Completion and Output

As a result of the cost overruns, BHP said it will recognise an impairment charge of about $2.3 billion for the potash project. It maintained its annual capital expenditure forecast at $11 billion for 2027 financial year.

The firm said that Stage 2 is 16% complete as of May-end and is expected to deliver around 4.36 million metric tons per year.

Combined Output and Market Impact

The combined output of the project after a two-year ramp-up would be about 10% of total global potash production, BHP said.

(Reporting by Sneha Kumar in Bengaluru; Editing by Rashmi Aich, Varun H K and Diti Pujara)

Key Takeaways

  • Stage 2 investment estimate rises to US$6.9 billion from the US$4.9 billion approved in 2023, representing a US$2 billion increase due to inflation, design changes, productivity challenges and extra labour and materials (bhp.com).
  • BHP will book an impairment charge of approximately US$2.3 billion, reflecting the third time cost and schedule targets for the Jansen project have been exceeded (bhp.com).
  • Stage 1 costs have also climbed, with the total investment now at US$8.4 billion (up from US$5.7 billion at approval), although first production remains on track for mid‑2027; Stage 2 is 14–16% complete, now expected to begin production in late FY 2031 (bhp.com).

References

Frequently Asked Questions

Why is BHP booking a $2.3 billion charge for the Jansen potash project?
BHP is booking a $2.3 billion charge due to cost overruns caused by inflation, design and scope changes, lower productivity, and additional labor and material requirements.
When is first production from the Jansen potash project now expected?
First production from Jansen's second stage is now expected in late financial year 2031.
How much is the total estimated cost for the Jansen Stage 2 project?
The total investment estimate for Jansen Stage 2 is now $6.9 billion, up from $4.9 billion approved in 2023.
What proportion of global potash production will the Jansen project supply?
After a two-year ramp-up, the combined output from both stages will be about 10% of total global potash production.
How much progress has BHP made on Jansen Stage 2 as of May-end?
BHP reported that Jansen Stage 2 is 16% complete as of the end of May.

Tags

Related Articles

More from Finance

Explore more articles in the Finance category