Microsoft pulls out of UK data center deal with Nscale, Telegraph reports

Published by Global Banking & Finance Review

Posted on October 18, 2026

2 min read

· Last updated: October 18, 2026

Add as preferred source on Google

Microsoft Ends Nscale Loughton Data Center Deal in UK Over Power Issues

Microsoft Withdraws from Nscale Data Center Project

Oct 18 (Reuters) - Microsoft has pulled out of a data center deal with British cloud provider Nscale, Britain's Telegraph newspaper reported on Sunday.

The US tech giant, one of Nscale's two largest customers, recently terminated its agreement for the data center in Loughton, Essex, according to the report.

Reasons Behind the Termination

The newspaper did not specify why Microsoft withdrew from the project, and Microsoft did not immediately respond to Reuters requests for comment outside regular business hours.

Power Supply Delays Impacting the Project

The Telegraph report said Nscale had faced repeated delays with the project. National power grid officials, it reported, had told Nscale they did not expect a power supply for the data center until the 2030s.

Nscale's Response and Future Plans

"Our relationship with Microsoft remains strong and long-term, and this unfortunate London-wide grid issue has no impact on our other contracts," an Nscale spokesperson told Reuters.

"We remain committed to both the Loughton project and the UK, and we are exploring alternative power sources for the site, in addition to other expansion sites in the UK."

Nscale's Business and Market Position

Nscale filed for an initial public offering in the US last month, with Microsoft and Anthropic expected to be its major customers, according to its prospectus.

Services and Competitive Landscape

Nscale provides infrastructure, including compute, power and data centers, as well as software for training and running AI models.

The Nvidia-backed AI group, which competes against CoreWeave, Nebius, Crusoe and Lambda, has grown rapidly since its launch, scaling from $100 million to more than $103 billion in total contracted value in just two-and-a-half years.

(Reporting by Nethra Sailesh and Gnaneshwar Rajan in Bengaluru; Editing by Joe Bavier)

Key Takeaways

  • Microsoft withdrew from its Loughton, Essex data center deal due to power supply delays, with grid availability reportedly pushed into the early‑to‑mid‑2030s (neoteo.com).
  • The Loughton site, requiring up to 90 MW of capacity, faces UK Power Networks forecasts of grid connection delays of several years (neoteo.com).
  • Nscale insists its relationship with Microsoft remains strong; it is exploring alternative power sources such as gas fuel cells, and continues to advance other UK expansion plans (resultsense.com).
  • Nscale, backed by Nvidia, filed an IPO prospectus in the US last month, showing Microsoft and Anthropic account for approximately 85% of its $103 billion in total contracted value (flowverify.co).

References

Frequently Asked Questions

Why did Microsoft pull out of the Nscale data center deal?
Microsoft exited the Nscale data center deal in Loughton, Essex, due to repeated project delays and expected power supply issues that may not be resolved until the 2030s.
Will Nscale continue the Loughton data center project?
Nscale stated it remains committed to the Loughton project and is exploring alternative power sources and expansion sites in the UK.
What impact does the power grid issue have on Nscale's other contracts?
According to an Nscale spokesperson, the London-wide grid issue does not affect their other contracts or their long-term relationship with Microsoft.
Who are Nscale’s major customers and competitors?
Nscale’s major customers include Microsoft and Anthropic, and its competitors are CoreWeave, Nebius, Crusoe, and Lambda.
What services does Nscale provide?
Nscale provides infrastructure such as compute power, data centers, and software for training and running AI models.

Tags

Related Articles

More from Finance

Explore more articles in the Finance category